Projects
Real Problems. Proven Results.
Industrial challenges solved across pulp & paper, marine, power plants and more.
Case Study
Stora Enso
RepairOn-SiteMain drive shaft failed, 6-week OEM lead timeReverse-engineered and machined replacement in 48h
Welded, re-machined and balanced to spec. Full dimensional report provided. Part installed on-site by Adretec team within scheduled maintenance window.
72hTurnaround
0.02mmTolerance
€40kSaved vs replacement
Stora Enso
New PartsObsolete component, no supplier and no drawingsManufactured a new part from a worn sample
3D scanned the worn original, reverse-engineered the geometry and machined a replacement to OEM spec. Delivered ready to install.
5 daysLead time
0.01mmTolerance
Stora Enso
Gear ManufacturingCustom gear set, 10-week manufacturer lead timeManufactured spur and helical gears in days
Defined module, material and heat treatment from the worn sample, then manufactured and inspected the gear set in-house.
7 daysLead time
€25kSaved vs replacement

Production Stopped?
We turn around critical parts in 24–48 hours. No delays. No excuses.